Indian staff yet to resume work on key power transmission projects linked to Rooppur Nuclear Plant

Senior officers from Indian companies passionate about excessive vitality transmission initiatives in Bangladesh, which might presumably per chance per chance be a must-have for evacuating electrical energy from the Rooppur Nuclear Strength Plant (RNPP), have but to reach support to their jobs, raising issues about the progress of these initiatives.

“Few workers from KEC Global Small and Transrail Lighting fixtures Small (TTL) have returned, nonetheless none from Larsen & Toubro Small (L&T) or other companies have reach support,” a high legit from Strength Grid Bangladesh PLC said.

The legit clarified that the returning workers are largely in the community recruited transient employees and mid-stage officers from KEC, without a senior officers support on topic but.

Nonetheless, one more senior Strength Grid Bangladesh legit indicated that Indian workers from L&T are anticipated to rejoin the initiatives from September 24.

“We are in a position to glimpse them resume their work,” the legit said.

The return of Indian personnel has been delayed since all workers from Indian companies left Bangladesh following the autumn of the Awami League authorities on August 5, in the wake of a mass uprising. As a result, the transmission initiatives bright Indian contractors have reach to a standstill.

For the time being, Indian companies are engaged in 17 transmission initiatives across Bangladesh, with L&T, Transrail, and KEC being the foremost contractors. Rather loads of these initiatives are necessary for connecting the Rooppur NPP, scheduled to start up operation in December this year, to the national grid.

“The surprising departure of Indian contractor workers has created uncertainty round these excessive initiatives,” said the Strength Grid Bangladesh legit.

Larsen & Toubro, one amongst the major contractors, has been awarded main contracts to manufacture transmission infrastructure necessary for evacuating electrical energy from Bangladesh’s first nuclear vitality plant in Rooppur, Pabna. The company is to blame for installing 400kV and 230kV transmission lines, which might presumably per chance per chance be excessive parts of the grid synchronization and attempting out direction of for the RNPP’s first unit, now scheduled for completion in early 2025.

The transmission mission, estimated to model Tk 10,981 crore, is being financed essentially by Exim Bank (Tk 8,219 crore), with contributions from the Bangladesh authorities (Tk 1,527 crore) and Strength Grid Bangladesh (Tk 1,235 crore).

Per the Strength Grid Bangladesh PLC, the transmission mission involves 5 main programs—the 464km long 400kV transmission lines, along with a 13km river crossing; 205km long 230kV transmission lines, along with 7km river crossing; 400kV 5 Bay extensions; 230kV four bay extensions; and qualitative upgradation of Bangladesh vitality draw for frequency adjust and frequency tumble protection, protection draw, emergency adjust draw and other connected responsibilities.