Bangladesh halves power buying from India's Adani amid payment dispute

Bangladesh has halved the energy it buys from neighbouring India’s Adani Vitality, citing lower iciness test, executive officers told Reuters on Monday, amid disagreements over dues working into a total bunch of millions of bucks.

Adani, whose founder has been accused by US authorities of being desirous about a bribery draw in India, costs which he has denied, halved supply to Bangladesh on Oct. 31 over cost delays as the country battles a foreign alternate shortage.

Subsequently Bangladesh told Adani to withhold supplying simplest half of the energy for now, officers said, although this could well well also simply lend a hand paying its extinct dues.

“We were horrified and enraged when they slice our supply,” said Md. Rezaul Karim, chairperson of the voice-slip Bangladesh Vitality Growth Board (BPDB). “Cold weather test is now down, so now we contain told them there might be no such thing as a contain to slip every devices of the plant.”

Adani has been supplying energy under a 25-year contract signed in 2017 under ousted high minister Sheikh Hasina, from a $2-billion energy plant in India’s jap voice of Jharkhand that has two devices, every with capacity of about 800 megawatts.

A doc considered by Reuters confirmed the plant ran at simplest 41.82% capacity in November, the lowest this year, with one unit shut since Nov. 1.

Two BPDB sources said Bangladesh had sold about 1,000 MW a month from Adani closing iciness, including that Adani had asked the board when it can well well resume fashioned purchases, but had no longer got a definitive solution.

An Adani Vitality spokesperson said the firm used to be continuing supply to Bangladesh, although mounting dues were a necessary anguish, making plant operations unsustainable.

“We’re in fixed dialogue with senior officers of BPDB and the executive, who contain assured us that our dues will most definitely be cleared soon,” said the spokesperson.

The firm used to be assured Bangladesh would fulfil its commitments, appropriate as Adani had upheld its contract responsibilities, he added.

Karim said Bangladesh owed Adani about $650 million, and paid about $85 million closing month and $97 million in October.

An Adani Vitality source, talking on situation of anonymity, said the dues had jumped to about $900 million, hurting its debt profile and risking a elevated cost of funds.

Bangladesh wants to sharply lower costs under the Adani deal, except it is a long way cancelled by a court docket, which has known as for an investigation into it, the de facto minister for energy and energy told Reuters on Sunday.

The Adani Vitality spokesperson said the firm had no indication that Bangladesh used to be reviewing its energy aquire pact.

Adani costs the excellent rate of all Indian suppliers to Bangladesh, a executive doc considered by Reuters confirmed.

Its cost per unit used to be 14.87 taka at some stage within the fiscal year that ended on June 30 2024, when compared with a median of 9.57 for all Indian suppliers.

The retail value in Bangladesh is 8.95 taka a unit, main to an annual energy subsidy invoice of 320 billion taka ($2.7 billion).

“For the reason that costs are high, the executive has to subsidise,” said Muhammad Fouzul Kabir Khan, Bangladesh’s energy and energy adviser. “We’d esteem energy costs, no longer simplest from Adani, to come down under the life like retail costs.”